Thermal Power Plant Boxberg, Germany

Principal: Vattenfall Europe Generation AG & Co. KG

Realisation Period: May 2007 – January 2008

Services: Detailed engineering for boiler house

For Vattenvall Europe as principal, Hitachi Power Europe GmbH is constructing the new power block R at the power plant site Boxberg.

The company Plauen Stahl Technologie GmbH is manufacturing and supplying the steel structure for the Boiler House and the buildings.

AIC is responsible for the detailed engineering of the steel structure at boiler house area.

Total Investment: 800 million EUR

Steel Structure:   6,000t