Integrating a ventilation system in Zwickau, Germany

Principal: Deutsche Telekom Immobilien und Service GmbH

Realisation Period: 2004

Services: Technical Facilities

AIC was responsible for the integration of a new ventilation system within a building of the Deutsche Telekom (switching center). Amongst other, AIC was engineering the move-in of the components with a capacity of 15,000 m³/h each. The outer connection points were realized via weather protected meshes in the outer walls of the central ventilation unit.

Construction Costs: 0.5 mill. EUR